Granted

Rue Général Molitor 4

Etterbeek · PU/405356 · Permis d'urbanisme privé

Rue Général Molitor 4, Etterbeek: extension or raising. Case octroyé, lodged on 18 July 2011. The decision was notified on 25 August 2011, 38 days after lodging.

régulariser la construction d'une véranda en façade arrière
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on18 July 2011date the file was received
Decision notified25 August 201138 days
Floor areasnot reported by the source
Competent authorityEtterbeek

Timeline

  1. Application lodged
  2. Declared complete
  3. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
14 mFaçade and windowsremplacer les châssis avec meneaux en béton par des châssis en aluminium en façade avant2023
70 mFaçade and windowsplacer une tente solaire rétractable au 3e étage, côté droit, en façade avant d'un immeuble à appartements2026
73 mExtension or raisingrégulariser une annexe au rez arrière, les menuiseries en façade avant et agrandir une baie en façade avant d'une maison2024
77 mHeavy renovationrégulariser la transformation d'un appartement (1er étage)2021
79 mFaçade and windowspeindre la façade avant d'une maison unifamiliale2022

Other nearby cases : 05/PU/2038689, 05/PU/1916496, 05/PU/1962471, 05/PFD/2012265, 05/GOU_PU/2027836, 05/PU/1946993, 05/PU/1936331, 05/PU/2006796, 05/PU/1898058, 05/PU/1962416, 05/PU/1904771, 05/PU/1927928, 05/PU/1969805, 05/AA/2023249, 05/PU/1956830, 05/PFD/1946827, 05/PU/1947191, 05/PU/1820075, 05/PU/2008863, 05/PFD/1939640, 05/PU/1952752, 05/PU/1946002, 05/PU/1822088, 05/SFD/1864754, 05/PU/1972377