Rue Général Molitor 4
Etterbeek · PU/405356 · Permis d'urbanisme privé
Rue Général Molitor 4, Etterbeek: extension or raising. Case octroyé, lodged on 18 July 2011. The decision was notified on 25 August 2011, 38 days after lodging.
régulariser la construction d'une véranda en façade arrière| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 18 July 2011 | date the file was received |
| Decision notified | 25 August 2011 | 38 days |
| Floor areas | — | not reported by the source |
| Competent authority | Etterbeek |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 14 m | Façade and windows | remplacer les châssis avec meneaux en béton par des châssis en aluminium en façade avant | 2023 |
| 70 m | Façade and windows | placer une tente solaire rétractable au 3e étage, côté droit, en façade avant d'un immeuble à appartements | 2026 |
| 73 m | Extension or raising | régulariser une annexe au rez arrière, les menuiseries en façade avant et agrandir une baie en façade avant d'une maison | 2024 |
| 77 m | Heavy renovation | régulariser la transformation d'un appartement (1er étage) | 2021 |
| 79 m | Façade and windows | peindre la façade avant d'une maison unifamiliale | 2022 |
Other nearby cases : 05/PU/2038689, 05/PU/1916496, 05/PU/1962471, 05/PFD/2012265, 05/GOU_PU/2027836, 05/PU/1946993, 05/PU/1936331, 05/PU/2006796, 05/PU/1898058, 05/PU/1962416, 05/PU/1904771, 05/PU/1927928, 05/PU/1969805, 05/AA/2023249, 05/PU/1956830, 05/PFD/1946827, 05/PU/1947191, 05/PU/1820075, 05/PU/2008863, 05/PFD/1939640, 05/PU/1952752, 05/PU/1946002, 05/PU/1822088, 05/SFD/1864754, 05/PU/1972377
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)