Rue de l'Autonomie 21–23, Anderlecht: office conversion. Case octroyé, lodged on 18 August 2011. The decision was notified on 10 January 2012, 145 days after lodging. The project creates 85 m² of housing.
changer l'affectation du premier étage (bureau en logement)| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 18 August 2011 | date the file was received |
| Decision notified | 10 January 2012 | 145 days |
| Works started | 18 November 2014 | |
| Competent authority | Anderlecht |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Granted
- Works started
- event_works_ended
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 13 m | Change of use | changer l'usage du commerce en un bureau avec des équipements associés tels que des salles de réunion et des cafétérias, | 2021 |
| 30 m | Façade and windows | isoler le pignon gauche et mettre en conformité la façade avant | 2023 |
| 30 m | Façade and windows | isoler le pignon gauche | 2022 |
| 36 m | Extension or raising | transformer un appartement par l'intégration d’une terrasse arrière au volume intérieur | 2026 |
| 41 m | Change of use | rénover une façade classée et régulariser le changement de destination d’un garage en commerce au rez-de-chaussée droit | 2022 |
Other nearby cases : 01/PU/1953332, 01/SFD/1970742, 01/PU/1971877, 13/PU/1866756, 01/SFD/1926584, 01/PU/1866840, 01/PU/1848119, 01/PU/1958495, 01/PU/1823106, 13/PU/1827230, 13/GOU_PU/1855828, 01/PU/1952745, 13/PU/1960519, 01/PFD/1845988, 01/PU/1957060, 01/PU/1918446, 01/PU/1930402, 01/PU/2024499, 01/PU/1902751, 13/PU/2039415, 13/PFD/1936780, 13/PU/1863847, 01/PFD/1908069, 13/PU/1991909, 01/PU/2042872
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)