Place Bizet 25
Anderlecht · PU/409228 · Permis d'urbanisme privé
Place Bizet 25, Anderlecht: change of use. Case octroyé, lodged on 30 December 2011. The decision was notified on 26 May 2012, 148 days after lodging. The project creates 90 m² of housing.
changer l'affectation d'un rez-de-chaussée (centre médical) en logement + modifier les façades avant et arrière| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 30 December 2011 | date the file was received |
| Decision notified | 26 May 2012 | 148 days |
| Works started | 9 June 2012 | |
| Competent authority | Anderlecht |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Granted
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 16 m | Change of use | modifier la destination et la façade avant du rez-de-chaussée | 2023 |
| 17 m | Regularisation | Mettre en conformité un immeuble de logements | 2023 |
| 22 m | Change of use | modifier la destination et la façade avant au rez-de-chaussée | 2023 |
| 25 m | Extension or raising | mettre en conformité l'annexe arrière au 1er étage | 2023 |
| 49 m | Retail or horeca fit-out | mettre en conformité un snack (fermeture de la cour, modification de la vitrine commerciale, ajout de gaines techniques | 2026 |
Other nearby cases : 01/PU/1895422, 01/ECO/1915180, 01/GOU_PU/1907679, 01/PU/1858239, 01/PU/1911575, 01/PU/1834894, 01/PU/1837765, 01/PU/1997326, 01/PU/1938374, 01/PU/1980779, 01/PU/1912054, 01/PU/1928003, 04/PU/1932667, 01/SFD/1985501, 01/PU/1932888, 01/PU/2012877, 01/PU/1985794, 01/PU/1907188, 01/PU/1865892, 01/AA/1829437, 01/PU/2037612, 01/SFD/2018650, 01/PU/1950334, 01/PU/1929396, 01/PU/2039564
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)