Avenue de l'Horizon 53
Woluwe-Saint-Pierre · PU/466564 · Permis d'urbanisme privé
Avenue de l'Horizon 53, Woluwe-Saint-Pierre: heavy renovation. Case octroyé, lodged on 13 May 2003. The decision was notified on 25 August 2003, 104 days after lodging.
Construction d'une piscine souterraine, aménagement des abords et transformation de l'habitation| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 13 May 2003 | date the file was received |
| Public inquiry | 22 May 2003 – 7 May 2003 | |
| Consultation committee | 20 June 2003 | |
| Decision notified | 25 August 2003 | 104 days |
| Floor areas | — | not reported by the source |
| Competent authority | Woluwe-Saint-Pierre |
Timeline
- Public inquiry closed
- Application lodged
- Declared complete
- Public inquiry opened
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 51 m | Tree felling | Abattre l'’arbre concerné présente des signes avancés de maladie affectant sa stabilité et son état sanitaire général. A | 2025 |
| 51 m | Tree felling | abattre trois arbres remarquables en zone de recul | 2026 |
| 51 m | Tree felling | abattre 6 arbres en zone latérale et zone de cours et jardins | 2024 |
| 51 m | Tree felling | abattre 2 arbres | 2023 |
| 77 m | Tree felling | abattre un arbre en zone de recul | 2024 |
Other nearby cases : 19/AA/1931623, 19/PU/1912891, 19/AA/1834041, 19/PU/1842404, 19/PU/2020177, 19/AA/1866351, 19/PU/1843749, 19/PU/1992721, 19/PU/2039663, 19/PU/1900961, 19/PU/1927468, 19/PU/2014255, 19/PU/1950407, 19/PU/1843311, 19/AA/1852543, 19/PU/1972133, 19/PU/1996792, 19/PU/1952379, 19/PFD/1904975, 19/PU/1841727, 19/PU/2027921, 19/AA/1835208, 19/PFD/2028816, 19/PU/2024393, 19/PFU/2042563
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)