Montagne aux Ombres 9
Woluwe-Saint-Pierre · PU/467536 · Permis d'urbanisme privé
Montagne aux Ombres 9, Woluwe-Saint-Pierre: tree felling. Case octroyé, lodged on 25 January 2006. The decision was notified on 30 January 2006, 5 days after lodging.
abattre un arbre| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 25 January 2006 | date the file was received |
| Decision notified | 30 January 2006 | 5 days |
| Floor areas | — | not reported by the source |
| Competent authority | Woluwe-Saint-Pierre |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 42 m | Façade and windows | remplacement des châssis dans un appartement | 2023 |
| 42 m | Regularisation | regulariser un studio | 2023 |
| 51 m | Split into dwellings | régulariser la conciergerie et y réaménager un studio au rez-de-chaussée d'un immeuble à appartements | 2023 |
| 51 m | Regularisation | régulariser l’appartement du 3e étage gauche en façade avant de l'immeuble à appartements | 2024 |
| 51 m | Regularisation | régulariser l'appartement du 3e étage arrière gauche de l'immeuble à appartements | 2023 |
Other nearby cases : 19/PU/1892567, 19/PU/1939512, 19/PU/1973991, 19/PU/1969481, 19/PU/1810232, 19/PU/1913404, 19/PU/1942623, 19/PU/1979374, 19/PU/2017663, 19/PU/1971898, 19/PU/1961186, 19/AA/1825347, 19/PU/1991636, 19/PU/1851416, 19/SFD/1832886, 19/PU/1825102, 19/PU/1957617, 19/PU/1904870, 19/PU/1905011, 19/PU/1947685, 19/PU/1947231, 19/PFU/2020326, 19/PU/2020544, 19/PU/1944852, 19/SFD/1832199
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)