Avenue Orban 103, Woluwe-Saint-Pierre: new construction. Case octroyé, lodged on 15 January 2010. The decision was notified on 16 March 2010, 60 days after lodging.
Construction d'une villa unifamiliale 4 façades| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 15 January 2010 | date the file was received |
| Decision notified | 16 March 2010 | 60 days |
| Floor areas | — | not reported by the source |
| Competent authority | Woluwe-Saint-Pierre |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.