Val des Bécasses 19, Woluwe-Saint-Pierre: extension or raising. Case octroyé, lodged on 16 August 2011. The decision was notified on 20 December 2011, 126 days after lodging.
Extension et transformation de l'habitation unifamiliale 4 façades| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 16 August 2011 | date the file was received |
| Public inquiry | 19 September 2011 – 4 October 2011 | |
| Consultation committee | 13 October 2011 | |
| Decision notified | 20 December 2011 | 126 days |
| Works started | 1 February 2012 | |
| Floor areas | — | not reported by the source |
| Competent authority | Woluwe-Saint-Pierre |
Timeline
- Application lodged
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 21 m | Tree felling | Abattre 3 arbres | 2022 |
| 28 m | Tree felling | Abattre 1 arbre en zone de recul et 1 arbre en zone de cours et jardins | 2023 |
| 48 m | Façade and windows | isoler par l'extérieur les façades d'une maison unifamiliale | 2025 |
| 55 m | Other | construire une piscine | 2022 |
| 79 m | New construction | construction d'une maison unifamiliale 4 façades | 2022 |
Other nearby cases : 19/AA/1908022, 19/AA/1855449, 19/PU/2010510, 19/PU/1973778, 19/PU/1972865, 19/PFD/1910302, 19/PFD/1933128, 19/AA/1823822, 19/AA/1850462, 19/AA/1862905, 19/PU/2011414, 19/AA/1867904, 19/AA/1913098, 19/PU/1849901, 19/PU/1914642, 19/PU/2004978, 19/PU/2021266, 19/AA/1892746