Granted
Rue de Zuen
Anderlecht · PU/472356 · Permis d'urbanisme privé
Rue de Zuen, Anderlecht: new construction. Case octroyé, lodged on 13 July 2012. The decision was notified on 15 November 2013, 490 days after lodging. The project creates 124 m² of housing.
réaliser un centre de tri124m²
Housing floor area created
| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 13 July 2012 | date the file was received |
| Public inquiry | 2 May 2013 – 17 May 2013 | |
| Consultation committee | 4 July 2013 | |
| Decision notified | 15 November 2013 | 490 days |
| Competent authority | Anderlecht |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.