Boulevard Industriel 8

Anderlecht · PU/473559 · Permis d'urbanisme privé

Boulevard Industriel 8, Anderlecht: heavy renovation. Case octroyé, lodged on 14 August 2012. The decision was notified on 5 June 2013, 295 days after lodging.

séparer deux immeubles, placer des portes sectionnelles et une clôture
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on14 August 2012date the file was received
Decision notified5 June 2013295 days
Competent authorityAnderlecht

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.