Boulevard Industriel 14

Anderlecht · PU/476907 · Permis d'urbanisme privé

Boulevard Industriel 14, Anderlecht: extension or raising. Case octroyé, lodged on 28 September 2012. The decision was notified on 18 March 2013, 171 days after lodging.

agrandir un hall industriel et construire des bureaux, réaménager le parking
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on28 September 2012date the file was received
Public inquiry28 November 2012 – 13 December 2012
Consultation committee19 December 2012
Decision notified18 March 2013171 days
Competent authorityAnderlecht

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Public inquiry opened
  5. Public inquiry closed
  6. Consultation committee
  7. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
0 mExtension or raisingRemplacer le parking étagé (non construit) par une extension du parking existant, ajouter un parking motos et un parking2022
0 mNew constructionPlacer 2 containers vestiaires/douches hommes et femmes pour une durée de limitée à 2 ans, le temps d'aménager des nouve2024
0 mOtherAménager un parking pour 196 véhicules légers à l'air libre et pour 167 véhicules légers couverts2023
161 mDemolition and reconstructionDémolir l’imprimerie et construire un pôle de logistique urbaine2026
232 mRetail or horeca fit-outplacer un show-case de 39m³2024

Other nearby cases : 01/SFD/1986301

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)