Avenue de Berchem-Sainte-Agathe 27
Koekelberg · PU/481167 · Permis d'urbanisme privé
Avenue de Berchem-Sainte-Agathe 27, Koekelberg: roof. Case octroyé, lodged on 3 January 2013. The decision was notified on 20 March 2015, 806 days after lodging.
mise en conformité du volume de l'édicule et des terrasses du duplex (3e et 4e étages)| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 3 January 2013 | date the file was received |
| Public inquiry | 13 May 2013 – 28 May 2013 | |
| Consultation committee | 13 September 2013 | |
| Decision notified | 20 March 2015 | 806 days |
| Competent authority | Koekelberg |
Timeline
- Application lodged
- Public inquiry opened
- Declared complete
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 16 m | Extension or raising | transformer une terrasse en zone arrière | 2024 |
| 25 m | Façade and windows | isoler le pignon latéral de l'immeuble du côté droit (bâtiment n°21) | 2023 |
| 42 m | Extension or raising | mettre en conformité la fermeture d'une terrasse au 1er étage en façade arrière | 2022 |
| 48 m | Change of use | Régularisation de la modif. esthétique de la façade à rue (remplacement des menuiseries extérieures et de la porte de ga | 2026 |
| 57 m | Façade and windows | changer les châssis en façade avant | 2022 |
Other nearby cases : 11/PU/1943541, 11/PU/1833303, 11/PU/1903717, 11/PU/2036993, 11/PFD/1977792, 11/PU/1995484, 11/PP/1820189, 11/PU/1821517, 11/PU/2035446, 11/PU/1846339, 11/PU/1968766, 11/PU/1900656, 11/PU/2038785, 11/PU/1950344, 11/PU/1970156, 11/GOU_PU/1826483, 11/PFD/1799444, 11/PU/1941755, 11/PU/1843516, 11/PU/1900635, 11/SFD/1811009, 11/PU/1917548, 11/PU/1977337, 11/PU/1938435, 11/PU/1992705
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)