Avenue Emile Max 173
Schaerbeek · PU/484972 · Permis d'urbanisme privé
Avenue Emile Max 173, Schaerbeek: extension or raising. Case octroyé, lodged on 25 March 2013. The decision was notified on 9 January 2014, 290 days after lodging. The project creates 64 m² of housing.
REALISE - Immeuble de 5 appartements: rehausser d'un étage un immeuble de 5 appartements afin d'agrandir le logement du dernier étage| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 25 March 2013 | date the file was received |
| Public inquiry | 7 November 2013 – 22 November 2013 | |
| Consultation committee | 5 December 2013 | |
| Decision notified | 9 January 2014 | 290 days |
| Works started | 28 October 2015 | |
| Competent authority | Schaerbeek |
Timeline
- Application lodged
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
- Works started
- event_works_ended
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 8 m | Change of use | dans un immeuble à usage mixte (un bureau et cinq logements), mettre en conformité le changement d’affectation du rez-de | 2023 |
| 39 m | Demolition and reconstruction | dans un bâtiment à usage mixte (bureau et logement), démolir et reconstruire les annexes arrière (rez-de-chaussée et 1er | 2024 |
| 39 m | Tree felling | Abattre un cerisier du Japon dans le jardin | 2023 |
| 52 m | Tree felling | abattre 8 arbres à haute-tige (acer pseudoplatanus) | 2022 |
| 56 m | Merger of dwellings | dans immeuble de 17 logements, réunir les deux appartements du 8ème étage (passe de 17 à 16 unités) en un seul logement, | 2022 |
Other nearby cases : 15/PU/1942645, 15/GOU_PU/2016923, 15/PU/1938685, 15/PU/1823176, 15/PU/1948056, 15/PU/2007484, 15/PU/1831755, 15/PU/2001249, 15/PFD/1839308, 15/PU/1842596, 15/PU/1948515, 15/PU/1956144, 15/PU/1844308, 15/PU/1938375, 15/PU/1930319, 15/PU/1829908, 15/PU/1917284, 15/GOU_PU/1968733, 15/PU/1910024, 15/PU/1846961, 15/PU/1941917, 15/PU/1832853, 15/PU/1963861, 15/PU/2001072, 15/PFD/2001781