Granted
Rue de Termonde 210
Ganshoren · PU/492377 · Permis d'urbanisme privé
Rue de Termonde 210, Ganshoren: split into dwellings. Case octroyé, lodged on 24 September 2013. The decision was notified on 5 March 2014, 162 days after lodging. The project creates 865 m² of housing. It comprises 5 dwellings.
rénover un bâtiment industriel (aménagement de 5 logements, 5 emplacements de parking et 3 zones d'entrepôts)865m²
Housing floor area created
5
Dwellings created
| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 24 September 2013 | date the file was received |
| Public inquiry | 20 January 2014 – 4 February 2014 | |
| Consultation committee | 18 February 2014 | |
| Decision notified | 5 March 2014 | 162 days |
| Works started | 28 January 2015 | |
| Competent authority | Ganshoren |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)