Rue Houzeau de Lehaie 56
Koekelberg · PU/492530 · Permis d'urbanisme privé
Rue Houzeau de Lehaie 56, Koekelberg: change of use. Case octroyé, lodged on 30 September 2013. The decision was notified on 31 March 2014, 182 days after lodging. The project creates 96 m² of housing.
réaménager le rez-de-chaussée d'un immeuble à appartements avec changement de destination de la partie « bureau » en logement| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 30 September 2013 | date the file was received |
| Decision notified | 31 March 2014 | 182 days |
| Competent authority | Koekelberg |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
- event_works_ended
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 19 m | Split into dwellings | Mettre en conformité les différents aménagements apportés aux logemenst existants, régulariser la création de 2 logement | 2021 |
| 46 m | Roof | aménager une toiture plate en terrasse en façade avant | 2021 |
| 46 m | Roof | aménager une toiture plate en terrasse en façade avant | 2023 |
| 52 m | Change of use | Changer l' affectation de l' atelier en commerce HORECA,Réaménagement intérieur sous-sol et RDC et régulariser annexe fa | 2021 |
| 65 m | Energy works | regulariser l'installation d'une pompe à chaleur | 2023 |
Other nearby cases : 11/PU/1985061, 11/PU/2019012, 11/PU/1832496, 11/PU/1922820, 11/PU/2042743, 11/PU/1904116, 11/PU/1964033, 12/PU/2038961, 11/PU/1953020, 12/PU/1913479, 11/SFD/1894394, 12/PU/1836036, 12/PU/2037132, 11/PU/1831187, 12/PU/2038787, 12/PU/2042840, 12/GOU_PU/1865434, 12/SFD/1867741, 12/PU/1860358, 12/PU/2017238, 11/PU/1900879, 11/PU/1943422, 11/PU/1824662, 11/PU/1861220, 12/PU/1956477
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)