Skip to content
AltUrb
Granted

Boulevard du Souverain 147A

Auderghem · PU/492660 · Permis d'urbanisme privé

Boulevard du Souverain 147A, Auderghem: energy works. Case octroyé, lodged on 27 September 2013. The decision was notified on 6 June 2014, 252 days after lodging.

régulariser les unités de HVAC (en façade arrière du rez-de-chaussée)
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on27 September 2013date the file was received
Public inquiry14 November 2013 – 29 November 2013
Consultation committee12 December 2013
Decision notified6 June 2014252 days
Floor areasnot reported by the source
Competent authorityAuderghem

Timeline

  1. Application lodged
  2. Public inquiry opened
  3. Public inquiry closed
  4. Consultation committee
  5. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
14 mChange of usemettre en conformité le changement d'affectation d'une partie du rez-de-chaussée, isoler la façade arrière, les murs mit2024
23 mHeavy renovationtransformer deux immeubles2026
26 mChange of usechanger la destination du commerce2026
51 mChange of usechanger la destination d'une boucherie en restaurant ainsi que créer deux ouvertures et installer la climatisation sur l2026
59 mSigns and advertisingplacer 2 enseignes2022

Other nearby cases : 02/GOU_PU/1870552, 02/PU/1841230, 02/PP/1906459, 02/PU/1828260, 02/PU/1922659, 02/ENS/1966796, 02/PU/1955524, 02/PU/1966811, 02/PU/2026770, 02/PU/1988663, 02/PU/1973241, 02/PU/1858471, 02/PU/1925153, 02/PU/1949551, 02/PU/1801301, 02/PU/2019426, 02/PU/1907206, 02/PU/2011985, 02/PU/1924580, 02/PU/1833449, 02/PU/1864369, 02/AA/1922273, 02/ENS/2005958, 02/PP/1839526, 02/PU/1953202

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)