Granted
Avenue de Bâle 1
Evere · PU/493178 · Permis d'urbanisme privé
Avenue de Bâle 1, Evere: demolition. Case octroyé, lodged on 16 October 2013. The decision was notified on 20 December 2013, 65 days after lodging.
démolir un bâtiment affecté à l'activité productive (activité de haute technologie - recherche en laboratoire) et supprimer les voies de circulation et parking sur le site.
| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 16 October 2013 | date the file was received |
| Public inquiry | 4 November 2013 – 19 November 2013 | |
| Consultation committee | 21 November 2013 | |
| Decision notified | 20 December 2013 | 65 days |
| Competent authority | Evere |
Timeline
- Application lodged
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 120 m | Signs and advertising | het plaatsen op het grond van een vastgemaakt uithangbord (totem) _ SANS SUITE | 2025 |
| 120 m | Energy works | het plaatsen van laadinfrastructuur en een transformatorcabine op een bestaand parking _ SANS SUITE | 2025 |
| 138 m | Change of use | Changer l'affectation du bâtiment situé à Avenue de Croydon 5 à Haren (Ville de Bruxelles).Transformer l’utilisation act | 2025 |
| 165 m | Change of use | Modifier la destination d'une partie du bâtiment de bureaux et grand commerce spécialisé en activités productives, const | 2022 |
| 203 m | Extension or raising | Installer deux bornes de recharges pour véhicules électriques et construire 4 places de stationnement spécifiques. Inst | 2022 |
Other nearby cases : 04/PU/1918083, 04/PU/1863125, 06/PU/2019253, 06/PU/2019208
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)