Granted
Avenue Louis Piérard 39 A
Evere · PU/494166 · Permis d'urbanisme privé
Avenue Louis Piérard 39 A, Evere: new construction. Case octroyé, lodged on 13 November 2013. The decision was notified on 31 July 2014, 260 days after lodging. The project creates 440 m² of housing. It comprises 4 dwellings.
construire un immeuble de 4 logements.440m²
Housing floor area created
4
Dwellings created
| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 13 November 2013 | date the file was received |
| Decision notified | 31 July 2014 | 260 days |
| Competent authority | Evere |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.