Granted
Boulevard Baudouin
Bruxelles · PU/507776 · Permis d'urbanisme privé
Boulevard Baudouin, Bruxelles: demolition and reconstruction. Case octroyé, lodged on 23 May 2000. The decision was notified on 5 July 2001, 408 days after lodging.
- démolir un bâtiment de deux niveaux - construire un immeuble à usage d'ambassade (équipement) avec au rez une surface commerciale, au 1er étage des bureaux, aux 4e, 5e et 6e étages des appartements, en sous-sol un garage-parking (74 pl.) - nouveau dossier 15B/05| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 23 May 2000 | date the file was received |
| Public inquiry | 27 October 2000 – 11 November 2000 | |
| Consultation committee | 21 November 2000 | |
| Decision notified | 5 July 2001 | 408 days |
| Floor areas | — | not reported by the source |
| Competent authority | Bruxelles |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)