Rue du Houblon, Bruxelles: heavy renovation. Case octroyé, lodged on 17 September 1999. The decision was notified on 2 March 2000, 167 days after lodging.

apporter des transformations à une construction existante : transformer partiellement le sous-sol de la zone 2 du complexe immobilier (aménagement de caves supplémentaires)
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on17 September 1999date the file was received
Decision notified2 March 2000167 days
Floor areasnot reported by the source
Competent authorityBruxelles

Timeline

  1. Application lodged
  2. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.