Rue du Bruel 53

Bruxelles · PU/509343 · Permis d'urbanisme privé

Rue du Bruel 53, Bruxelles: extension or raising. Case octroyé, lodged on 29 October 1998. The decision was notified on 28 December 1999, 425 days after lodging.

het bouwen van een uitbreiding aan een bestaande werkplaats (van 938 m² naar 1.284 m²)
The application's own description, in its source language (NL). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on29 October 1998date the file was received
Decision notified28 December 1999425 days
Floor areasnot reported by the source
Competent authorityBruxelles

Timeline

  1. Application lodged
  2. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.