Granted
Avenue du Bourget (21e afd–sec C deel)
Bruxelles · PU/509586 · Permis d'urbanisme privé
Avenue du Bourget (21e afd–sec C deel), Bruxelles: new construction. Case octroyé, lodged on 8 July 1998. The decision was notified on 11 March 1999, 246 days after lodging.
het bouwen van een gebouw voor hoogtechnologische activiteiten (wijziging stedenbouwkundige vergunning voor het dossier 32B/97, afgeleverd op 18/11/1997)| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 8 July 1998 | date the file was received |
| Decision notified | 11 March 1999 | 246 days |
| Floor areas | — | not reported by the source |
| Competent authority | Bruxelles |
Timeline
- Application lodged
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.