Rue de Namur 35–37
Bruxelles · PU/512478 · Permis d'urbanisme privé
Rue de Namur 35–37, Bruxelles: split into dwellings. Case octroyé, lodged on 17 July 2002. The decision was notified on 19 February 2003, 217 days after lodging. It comprises 3 dwellings.
transformation d'un commerce et d'un logement unifamilial en un commerce et 3 appartements| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 17 July 2002 | date the file was received |
| Consultation committee | 15 October 2002 | |
| Decision notified | 19 February 2003 | 217 days |
| Floor areas | — | not reported by the source |
| Competent authority | Bruxelles |
Timeline
- Application lodged
- Declared complete
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 16 m | Retail or horeca fit-out | transformer l'utilisation d'un rez-de-chaussée commercial en café (régularisation) ; modifier la façade avant en remplaç | 2023 |
| 29 m | Signs and advertising | placer une enseigne parallèle, une enseigne perpendiculaire et une tente solaire avec une enseigne sur la bordure flotta | 2022 |
| 67 m | Merger of dwellings | réunir 2 logements au 3ème étage, modifier l’aménagement du sous-sol, créer une coursive extérieure en façade arrière (m | 2025 |
| 86 m | Energy works | PV-Installatie (Fotovoltaïsche zonnepanelen) | 2026 |
| 89 m | New construction | Supprimer 72 emplacements de parkings, régulariser la création d'une baie entre deux poches de parking ainsi que constru | 2022 |
Other nearby cases : 04/PFD/1848957, 04/PU/1949374, 04/PU/1962482, 04/PU/2024099, 04/PU/2024096, 04/PU/1909808, 04/PU/1968416, 04/PU/1857455, 04/PU/1940208, 04/PFU/1829728, 04/PFU/1848643, 04/PFU/1909971, 04/PFU/1981905, 04/PFD/1922764, 04/PU/2022126, 04/PU/1961208, 04/PU/2023160, 04/PU/1937294, 04/PU/2043415, 04/PU/2007406, 04/PU/2022266, 04/PU/2020288, 04/PU/2011875, 04/PFD/1972026, 04/PFD/1906869
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)