Granted

Rue Bruyn

Bruxelles · PU/513457 · Permis d'urbanisme privé

Rue Bruyn, Bruxelles: new construction. Case octroyé, lodged on 25 June 2004. The decision was notified on 28 December 2005, 551 days after lodging.

construction d'un immeuble à appartements
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on25 June 2004date the file was received
Public inquiry27 May 2005 – 11 June 2005
Consultation committee21 June 2005
Decision notified28 December 2005551 days
Floor areasnot reported by the source
Competent authorityBruxelles

Timeline

  1. Application lodged
  2. Declared complete
  3. Public inquiry opened
  4. Public inquiry closed
  5. Consultation committee
  6. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)