Altaica Urban
Refused

Quai des Usines 158A

Bruxelles · PU/515029 · Permis d'urbanisme privé

Quai des Usines 158A, Bruxelles: change of use. Case refusé, lodged on 16 March 2006. The decision was notified on 14 November 2006, 243 days after lodging.

réaffectation du niveau -1 en lieu de culte
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusRefusé
Lodged on16 March 2006date the file was received
Decision notified14 November 2006243 days
Floor areasnot reported by the source
Competent authorityBruxelles

Timeline

  1. Application lodged
  2. Declared complete
  3. Decision notified · Refused

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.