Skip to content
Altaica Urban
Granted

Chaussée de Vilvorde 214

Bruxelles · PU/515674 · Permis d'urbanisme privé

Chaussée de Vilvorde 214, Bruxelles: demolition and reconstruction. Case octroyé, lodged on 24 June 2005. The decision was notified on 28 December 2005, 187 days after lodging.

Démantèlement des tanks n°116 et 117, reconstruction du tank n°117 et rénovation et déplacement du tank n°118 (modifications du P.U. (11V/03))
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on24 June 2005date the file was received
Decision notified28 December 2005187 days
Floor areasnot reported by the source
Competent authorityBruxelles

Timeline

  1. Application lodged
  2. Declared complete
  3. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
72 mEnergy worksRéaliser des travaux éléctriques et de génie civil dans l'enceinte du poste haute tension de Marly Placer des nouveaux 2021
242 mExtension or raisingd’une part, réaménager un centre de données, modifier les façades, rehausser le local technique, agrandir l’abri à vélos2025
242 mTree fellingabattre 30 arbres à haute tige en vue de construire un datacenter (permis A387/2019 et A536/2020)2024

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)