Granted
Laskouter
Bruxelles · PU/518161 · Permis d'urbanisme privé
Laskouter, Bruxelles: new construction. Case octroyé, lodged on 31 May 2007. The decision was notified on 29 May 2008, 364 days after lodging.
construction d'un logement unifamilial (352 m²)| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 31 May 2007 | date the file was received |
| Public inquiry | 11 October 2008 – 26 January 2008 | |
| Consultation committee | 5 February 2008 | |
| Decision notified | 29 May 2008 | 364 days |
| Floor areas | — | not reported by the source |
| Competent authority | Bruxelles |
Timeline
- Application lodged
- Declared complete
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
- Public inquiry opened
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)