Granted
Rue Bruyn 39
Bruxelles · PU/520197 · Permis d'urbanisme privé
Rue Bruyn 39, Bruxelles: new construction. Case octroyé, lodged on 1 October 2009. The decision was notified on 30 June 2010, 272 days after lodging.
construction d'une maison unifamiliale| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 1 October 2009 | date the file was received |
| Public inquiry | 11 December 2009 – 26 December 2009 | |
| Consultation committee | 5 January 2010 | |
| Decision notified | 30 June 2010 | 272 days |
| Floor areas | — | not reported by the source |
| Competent authority | Bruxelles |
Timeline
- Application lodged
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 68 m | Façade and windows | remplacer les châssis, la porte d’entrée et la porte de garage, ajouter des volets roulants aux 1er et 2ème étages et aj | 2024 |
| 76 m | New construction | construire une maison unifamiliale | 2022 |
| 76 m | New construction | construire une maison unifamiliale | 2023 |
| 140 m | Public space | Modifier le permis de réf. 04/PFD/1956273 : déplacer légèrement la sanisette, suite à la demande de Sillbelga, afin de l | 2026 |
| 141 m | Public space | Placer une sanisette près de la zone terminus des bus "Val Maria". | 2024 |
Other nearby cases : 04/PU/1838575, 04/GOU_PU/1841184, 04/PU/1799955
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)