Skip to content
Altaica Urban
Granted

Quai Léon Monnoyer 11

Bruxelles · PU/521081 · Permis d'urbanisme privé

Quai Léon Monnoyer 11, Bruxelles: new construction. Case octroyé, lodged on 21 January 2009. The decision was notified on 30 March 2010, 433 days after lodging.

Inrichting van een overslag en stockage plaats voor minerale producten en optrekken van keermuren en plaatsen van een weegbrug
The application's own description, in its source language (NL). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on21 January 2009date the file was received
Public inquiry12 June 2006 – 27 June 2009
Consultation committee7 July 2009
Decision notified30 March 2010433 days
Floor areasnot reported by the source
Competent authorityBruxelles

Timeline

  1. Public inquiry opened
  2. Application lodged
  3. Public inquiry closed
  4. Consultation committee
  5. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)