Granted
Quai des Armateurs (poste 12)
Bruxelles · PU/521419 · Permis d'urbanisme privé
Quai des Armateurs (poste 12), Bruxelles: demolition and reconstruction. Case octroyé, lodged on 1 October 2008. The decision was notified on 25 November 2009, 420 days after lodging.
démolition des installations existantes et reconstruction d'une nouvelle centrale à bétons. ( voir PE 084A/08)| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 1 October 2008 | date the file was received |
| Public inquiry | 22 May 2009 – 6 June 2009 | |
| Consultation committee | 16 June 2009 | |
| Decision notified | 25 November 2009 | 420 days |
| Floor areas | — | not reported by the source |
| Competent authority | Bruxelles |
Timeline
- Application lodged
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)