Granted
Noendelle (kavel 4)
Bruxelles · PU/522498 · Permis d'urbanisme privé
Noendelle (kavel 4), Bruxelles: new construction. Case octroyé, lodged on 9 January 2012. The decision was notified on 11 July 2012, 184 days after lodging.
bouwen van een eengezinswoning| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 9 January 2012 | date the file was received |
| Public inquiry | 24 February 2012 – 10 March 2012 | |
| Consultation committee | 20 March 2012 | |
| Decision notified | 11 July 2012 | 184 days |
| Floor areas | — | not reported by the source |
| Competent authority | Bruxelles |
Timeline
- Application lodged
- Public inquiry opened
- Declared complete
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.