Rue de Ciplet 11

Bruxelles · PU/522689 · Permis d'urbanisme privé

Rue de Ciplet 11, Bruxelles: new construction. Case octroyé, lodged on 25 November 2011. The decision was notified on 18 April 2013, 510 days after lodging. It comprises 5 dwellings.

construction d'un nouvel immeuble à 5 appartements
The application's own description, in its source language (FR). Source: Nova.
5
Dwellings created
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on25 November 2011date the file was received
Public inquiry25 August 2012 – 9 September 2012
Consultation committee18 September 2012
Decision notified18 April 2013510 days
Works started18 April 2015
Floor areasnot reported by the source
Competent authorityBruxelles

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Public inquiry opened
  4. Public inquiry closed
  5. Consultation committee
  6. Decision notified · Granted
  7. Works started
  8. Declared complete

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.