Quai des Usines 158–154
Bruxelles · PU/522722 · Permis d'urbanisme privé
Quai des Usines 158–154, Bruxelles: demolition and reconstruction. Case octroyé, lodged on 17 November 2011. The decision was notified on 31 July 2012, 257 days after lodging.
démolir et construire| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 17 November 2011 | date the file was received |
| Decision notified | 31 July 2012 | 257 days |
| Works started | 21 August 2012 | |
| Floor areas | — | not reported by the source |
| Competent authority | Bruxelles |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 82 m | Heavy renovation | Adapter l'implantation des garde-corps extérieurs, ainsi que l’ajout de nouveaux éléments strictement identiques à ceux | 2026 |
| 82 m | Façade and windows | Remplacer des châssis non d'origine extérieurs par de nouveaux châssis en bois suivant le modèle d'origine y compris le | 2022 |
| 101 m | Change of use | changer la destination d'une partie du rez-de-chaussée et du premier étage des "maisonnettes", de crêche vers un commerc | 2022 |
| 101 m | Change of use | Changement d'utilisation d’une crèche en un équipement d’intérêt collectif au centre commercial Docks Bruxsel. | 2026 |
| 144 m | Signs and advertising | placer un dispositif de publicité double-face éclairé de 16m² sur un terrain bâti | 2022 |
Other nearby cases : 04/PU/1865913, 04/GOU_PU/1898511, 04/PFD/1947933
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)