Skip to content
Altaica Urban
Granted

Avenue du Marly

Bruxelles · PU/524378 · Permis d'urbanisme privé

Avenue du Marly, Bruxelles: new construction. Case octroyé, lodged on 9 July 2010. The decision was notified on 17 February 2011, 223 days after lodging.

Nieuwbouw van een productiehal met bijbehorende kantoren, showroom en openluchtparking voor 31 voertuigen
The application's own description, in its source language (NL). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on9 July 2010date the file was received
Public inquiry10 September 2010 – 25 September 2010
Consultation committee5 October 2010
Decision notified17 February 2011223 days
Floor areasnot reported by the source
Competent authorityBruxelles

Timeline

  1. Application lodged
  2. Declared complete
  3. Public inquiry opened
  4. Public inquiry closed
  5. Consultation committee
  6. Decision notified · Granted
  7. Declared incomplete

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)