Granted
Allée Verte 3
Bruxelles · PU/524478 · Permis d'urbanisme privé
Allée Verte 3, Bruxelles: demolition and reconstruction. Case octroyé, lodged on 9 July 2012. The decision was notified on 17 June 2014, 708 days after lodging.
démolition et construction de 2 résidences pour jeunes travailleurs et étudiants avec 143 emplacements de parking ART.126/1 / démolition et construction de 2 résidences pour jeunes travailleurs et étudiants avec 140 emplacements de parking| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 9 July 2012 | date the file was received |
| Public inquiry | 24 May 2013 – 8 June 2013 | |
| Consultation committee | 8 October 2013 | |
| Decision notified | 17 June 2014 | 708 days |
| Works started | 29 March 2016 | |
| Floor areas | — | not reported by the source |
| Competent authority | Bruxelles |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)