Skip to content
Altaica Urban
Granted

Chaussée de Vilvorde 214

Bruxelles · PU/524790 · Permis d'urbanisme privé

Chaussée de Vilvorde 214, Bruxelles: operation of installations. Case octroyé, lodged on 3 October 2012. The decision was notified on 24 May 2013, 233 days after lodging.

plaatsen van een blusschuimtank van 4.500 liter in een inkuiping en plaatsen van een additieftank van 16.000 liter in een inkuiping GEMENGD DOSSIER (ref. M.V. 003V/2013)
The application's own description, in its source language (NL). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on3 October 2012date the file was received
Public inquiry25 January 2013 – 9 February 2013
Consultation committee19 February 2013
Decision notified24 May 2013233 days
Floor areasnot reported by the source
Competent authorityBruxelles

Timeline

  1. Application lodged
  2. Declared complete
  3. Public inquiry opened
  4. Public inquiry closed
  5. Consultation committee
  6. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
72 mEnergy worksRéaliser des travaux éléctriques et de génie civil dans l'enceinte du poste haute tension de Marly Placer des nouveaux 2021
242 mExtension or raisingd’une part, réaménager un centre de données, modifier les façades, rehausser le local technique, agrandir l’abri à vélos2025
242 mTree fellingabattre 30 arbres à haute tige en vue de construire un datacenter (permis A387/2019 et A536/2020)2024

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)