Boulevard Roi Albert II 128

Bruxelles · PU/524873 · Permis d'urbanisme privé

Boulevard Roi Albert II 128, Bruxelles: façade and windows. Case octroyé, lodged on 22 October 2012. The decision was notified on 8 July 2013, 259 days after lodging.

verbouwen van de gevel van het handelsgelijkvloers
The application's own description, in its source language (NL). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on22 October 2012date the file was received
Consultation committee19 March 2013
Decision notified8 July 2013259 days
Floor areasnot reported by the source
Competent authorityBruxelles

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Consultation committee
  5. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.