Skip to content
AltUrb
Granted

Rampe Romaine 8–10

Bruxelles · PU/525631 · Permis d'urbanisme privé

Rampe Romaine 8–10, Bruxelles: new construction. Case octroyé, lodged on 30 April 2013. The decision was notified on 30 October 2013, 183 days after lodging. It comprises 29 dwellings.

het bouwen van een appartementsgebouw met 29 woningen (wijzigen van de stedenbouwkundige vergunning 42R/09 afgeleverd op 24/11/11 verlengd tot 23/11/14)
The application's own description, in its source language (NL). Source: Nova.
29
Dwellings created
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on30 April 2013date the file was received
Public inquiry14 June 2013 – 29 June 2013
Consultation committee9 July 2013
Decision notified30 October 2013183 days
Floor areasnot reported by the source
Competent authorityBruxelles

Timeline

  1. Application lodged
  2. Public inquiry opened
  3. Declared complete
  4. Public inquiry closed
  5. Consultation committee
  6. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)