Skip to content
Altaica Urban
Granted

Avenue du Forum 1–5

Bruxelles · PU/526091 · Permis d'urbanisme privé

Avenue du Forum 1–5, Bruxelles: energy works. Case octroyé, lodged on 12 August 2013. The decision was notified on 6 February 2014, 178 days after lodging.

implantation d'une cabine de détente gaz (Sibelga) en vue de la mise en place d'un système de cogénération pour l'ensemble des immeubles de logements situés dans le parc Forum
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on12 August 2013date the file was received
Public inquiry20 September 2013 – 5 October 2013
Consultation committee15 October 2013
Decision notified6 February 2014178 days
Floor areasnot reported by the source
Competent authorityBruxelles

Timeline

  1. Application lodged
  2. Declared complete
  3. Public inquiry opened
  4. Public inquiry closed
  5. Consultation committee
  6. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
81 mTree fellingAbattre 16 bomen2024
81 mTree fellingAbattre 16 érables avenue du Forum à Bruxelles. dans le but de sécuriser le parking, replanter une haie est plus adéquat2025
81 mTree fellingAbattre 16 érables2025
103 mTree fellingabattre 6 arbres à haute tige (1 peuplier et 5 aulnes)2024
136 mFaçade and windowseffectuer des travaux structurels en façade, remplacer le bardage en pierre blanche par du crépi sur isolant beige, et c2022

Other nearby cases : 04/PU/1844724, 04/PU/1844701, 04/PU/1957467, 04/PU/1940779, 04/PU/1958641, 04/PU/1921806, 04/PU/1896921, 04/PU/2025454, 04/PU/2012910, 04/PU/2019405

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)