Chaussée de Buda 94–96, Bruxelles: demolition. Case octroyé, lodged on 3 September 2013. The decision was notified on 24 April 2014, 233 days after lodging.

gedeeltelijke afbraak van een leegstaand en vervallen bedrijfscomplex
The application's own description, in its source language (NL). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on3 September 2013date the file was received
Public inquiry24 January 2014 – 8 February 2014
Consultation committee18 February 2014
Decision notified24 April 2014233 days
Works started16 December 2014
Floor areasnot reported by the source
Competent authorityBruxelles

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Public inquiry opened
  5. Public inquiry closed
  6. Consultation committee
  7. Decision notified · Granted
  8. Works started

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
25 mChange of usemodifier la destination d’atelier en équipement d’intérêt collectif2023
37 mChange of useétendre l'Horeca du rez-de-chaussée jusqu'au 1er étage et modifier l'affectation du 1er étage de logement en commerce (r2024
106 mRegularisationrégulariser l'imperméabilisation partielle de parcelles situées en zone d'industrie / zone d'activités portuaires et de 2024
186 mOtherPoser des 18 câbles 36 kV en terrain privé, plus deux fibres optiques et aménager un revêtement perméable à l’eau.2023