Skip to content
AltUrb
Granted

Rue Picard 3

Bruxelles · PU/526436 · Permis d'urbanisme privé

Rue Picard 3, Bruxelles: new construction. Case octroyé, lodged on 29 October 2013. The decision was notified on 17 June 2014, 231 days after lodging.

modifier le permis d'urbanisme 21P/10 en ce qui concerne l'accès principal au site, l'aménagement de l'esplanade et le parking souterrain situé sous l'esplanade et construire un pavillon d'accès
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on29 October 2013date the file was received
Public inquiry3 January 2014 – 18 January 2014
Consultation committee28 January 2014
Decision notified17 June 2014231 days
Works started7 July 2014
Floor areasnot reported by the source
Competent authorityBruxelles

Timeline

  1. Application lodged
  2. Declared complete
  3. Public inquiry opened
  4. Public inquiry closed
  5. Consultation committee
  6. Decision notified · Granted
  7. Works started

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
26 mRoofAménagement d'une terrasse sur la toiture de l'Entrepôt Royal sur le site de Tour-et-Taxis2026
54 mSigns and advertisingplacer 3 enseignes parallèles (Tour & Taxis)2022
88 mChange of useChanger de destination et d'utilisation une partie des bâtiments A, B et E de Tour-et-Taxis.2025
111 mSigns and advertisingremplacer 1 mobilier urbain d’information avec support de publicité (BXL0492)2021
116 mPublic spaceremplacer un mobilier urbain d'information avec support de publicité (2m²) (BXL 0472)2024

Other nearby cases : 04/PFD/1992358, 04/PFD/2025541, 04/PFD/1900396, 04/PU/2039098, 04/PU/1810333, 04/PFD/1898711, 04/PFD/1870968, 04/PFD/1943670, 12/PU/2010939, 12/PU/2011088, 12/PU/1936802, 12/PU/1913535, 12/PU/1824454, 12/PU/1968291, 12/PU/1924946, 12/PU/1845459, 12/PU/1896379, 12/PFD/1851509, 12/PU/1829593, 04/PU/1828560, 04/PU/1895758, 04/PFD/2033397, 04/PU/1838593, 12/PU/1821218

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)