Granted

Rue Edmond Delcourt 17a

Anderlecht · PU/527517 · Permis d'urbanisme privé

Rue Edmond Delcourt 17a, Anderlecht: extension or raising. Case octroyé, lodged on 21 May 2014. The decision was notified on 11 December 2014, 204 days after lodging.

mettre en conformité la création d'une terrasse et l'extension d'un appartement
The application's own description, in its source language (FR). Source: Nova.
1
Housing floor area removed
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on21 May 2014date the file was received
Decision notified11 December 2014204 days
Competent authorityAnderlecht

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
13 mRegularisationmettre en conformité une maison unifamiliale2024
13 mRegularisationmettre en conformité une maison unifamiliale2025
13 mRegularisationmettre en conformité une maison unifamiliale2024
24 mSplit into dwellingsmettre en conformité la division de l’habitation unifamiliale en deux logements.2025
39 mRegularisationmettre en conformité une maison unifamiliale2023

Other nearby cases : 01/PU/1992931, 01/PU/1899769, 01/PU/1856093, 01/PU/1824302, 01/SFD/1986444, 01/PU/1936609, 01/SFD/1867975, 01/PU/1998556, 01/GOU_PU/1996063, 01/PU/1829845, 01/PU/1980982, 01/PU/2035593, 01/PU/1859451, 01/PU/1993489, 01/PU/1949677, 01/PU/1967278, 01/SFD/2014469, 01/PFU/1948574, 01/PU/1859264, 01/PU/1934667, 01/PFD/1908346, 01/PFU/1820234, 01/PFU/1836035, 01/PU/1923406, 01/PU/1925001

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)