Granted
Clos André Rappe 6 à 22
Woluwe-Saint-Lambert · PU/539871 · Permis d'urbanisme privé
Clos André Rappe 6 à 22, Woluwe-Saint-Lambert: new construction. Case octroyé, lodged on 19 June 2006. The decision was notified on 27 March 2007, 281 days after lodging. It comprises 9 dwellings.
construire neuf maisons unifamiliales dans le périmètre du Plan de Lotissement n° 585 approuvé le 15/07/20039
Dwellings created
| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 19 June 2006 | date the file was received |
| Decision notified | 27 March 2007 | 281 days |
| Floor areas | — | not reported by the source |
| Competent authority | Woluwe-Saint-Lambert |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)