Granted
Chemin des Deux Maisons 63
Woluwe-Saint-Lambert · PU/540172 · Permis d'urbanisme privé
Chemin des Deux Maisons 63, Woluwe-Saint-Lambert: merger of dwellings. Case octroyé, lodged on 30 July 2007. The decision was notified on 31 October 2007, 93 days after lodging.
ouvrir une baie de porte entre deux appartements au 1er étage de l'immeuble| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 30 July 2007 | date the file was received |
| Decision notified | 31 October 2007 | 93 days |
| Floor areas | — | not reported by the source |
| Competent authority | Woluwe-Saint-Lambert |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 0 m | Extension or raising | régulariser l'extension de la terrasse du duplex situé aux 6ème et 7ème étages de l'immeuble | 2021 |
| 0 m | Regularisation | CLASSE SANS SUITE - régulariser la situation de fait (concernant les circulations verticales du bloc G) de l'immeuble | 2023 |
| 0 m | Office conversion | changer la destination de bureau en logement dans l'immeuble résidentiel | 2025 |
| 0 m | Roof | régulariser les modifications apportées par rapport à la situation de droit et aménager une terrasse sur la toiture plat | 2024 |
| 0 m | Change of use | changer la destination de bureau en logement dans l'immeuble résidentiel | 2024 |
Other nearby cases : 18/PU/1979768, 18/GOU_PU/1930658, 18/PFD/1911332, 18/PFD/2019726, 18/PFD/2005188, 18/PFD/1925021, 18/PFD/2040255, 18/PFD/1953562, 18/PFU/1897372, 18/PFU/1979934, 18/PFD/1926198, 18/PU/1945176, 18/PU/1953330, 18/PU/2001772