Granted
Chemin des Deux Maisons 69
Woluwe-Saint-Lambert · PU/540917 · Permis d'urbanisme privé
Chemin des Deux Maisons 69, Woluwe-Saint-Lambert: change of use. Case octroyé, lodged on 21 December 2009. The decision was notified on 21 May 2010, 151 days after lodging.
régulariser le changement d'affectation des commerces en bureaux au niveau du rez-de-chaussée de l'immeuble| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 21 December 2009 | date the file was received |
| Decision notified | 21 May 2010 | 151 days |
| Floor areas | — | not reported by the source |
| Competent authority | Woluwe-Saint-Lambert |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 0 m | Extension or raising | régulariser l'extension de la terrasse du duplex situé aux 6ème et 7ème étages de l'immeuble | 2021 |
| 0 m | Regularisation | CLASSE SANS SUITE - régulariser la situation de fait (concernant les circulations verticales du bloc G) de l'immeuble | 2023 |
| 0 m | Office conversion | changer la destination de bureau en logement dans l'immeuble résidentiel | 2025 |
| 0 m | Office conversion | changer l'affectation d'un bureau en logement | 2025 |
| 0 m | Roof | régulariser les modifications apportées par rapport à la situation de droit et aménager une terrasse sur la toiture plat | 2024 |
Other nearby cases : 18/PU/1958961, 18/PFD/1911332, 18/GOU_PU/1930658, 18/PFD/2019726, 18/PFD/2005188, 18/PFD/1925021, 18/PFD/2040255, 18/PFD/1953562, 18/PFU/1897372, 18/PFU/1979934, 18/PFD/1926198, 18/PU/1945176, 18/PU/1953330, 18/PU/2001772