Skip to content
Altaica Urban
Granted

Chemin des Deux Maisons

Woluwe-Saint-Lambert · PU/541757 · Permis d'urbanisme privé

Chemin des Deux Maisons, Woluwe-Saint-Lambert: new construction. Case octroyé, lodged on 31 August 2012. The decision was notified on 14 January 2014, 501 days after lodging. It comprises 126 dwellings.

construire 2 immeubles totalisant 125 logements et 140 places de parking en sous-sol#AU FINAL : 126 logements et 162 parkings
The application's own description, in its source language (FR). Source: Nova.
126
Dwellings created
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on31 August 2012date the file was received
Public inquiry21 March 2013 – 5 April 2013
Consultation committee19 April 2013
Decision notified14 January 2014501 days
Works started18 June 2014
Floor areasnot reported by the source
Competent authorityWoluwe-Saint-Lambert

Timeline

  1. Application lodged
  2. Declared complete
  3. Public inquiry opened
  4. Public inquiry closed
  5. Consultation committee
  6. Decision notified · Granted
  7. Works started

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)