Rue du Houblon 20–24
Bruxelles · PU/543562 · Permis d'urbanisme privé
Rue du Houblon 20–24, Bruxelles: change of use. Case octroyé, lodged on 11 July 2014. The decision was notified on 29 January 2016, 567 days after lodging.
transformer un ensemble industriel en commerce avec prise en compte de la structure portante| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 11 July 2014 | date the file was received |
| Consultation committee | 12 May 2015 | |
| Decision notified | 29 January 2016 | 567 days |
| Works started | 23 February 2016 | |
| Competent authority | Bruxelles |
Timeline
- Application lodged
- Consultation committee
- Decision notified · Granted
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 94 m | Heavy renovation | Rénover les locaux administratifs de la Croix Rouge, placer des châssis en bois naturel en façades, isoler les façades p | 2024 |
| 108 m | Other | Construire un relais de télécommunication mobile INSKY en toiture d'un bâtiment situé rue du Rempart aux Moines 135, B-1 | 2026 |
| 127 m | Public space | installer une terrasse annuelle de 49 m² sur l'espace public | 2023 |
| 136 m | Extension or raising | construire une extension sur la toiture du bâtiment et aménager une terrasse | 2022 |
| 137 m | Heavy renovation | Rénover et ouvrir au quartier le gymnase et la salle des fêtes de l'école. | 2024 |
Other nearby cases : 04/PU/1907509, 04/PU/1835933, 04/PU/2009683, 04/PU/1847895, 04/PU/1862073, 04/PU/1892290, 04/PU/1810574, 04/PU/1962407, 04/PU/2010206, 04/PU/1965446, 04/PU/1966950, 04/PU/1965099, 04/PU/1831431, 04/PFU/1992763, 04/PFU/1948045, 04/PU/2029710, 04/PU/1967665, 04/PU/1963102, 04/PU/1908034, 04/PU/1936651, 04/PU/1954537, 04/PFU/1954406, 04/PU/1989869, 04/PFD/2042402, 04/PU/2028649
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)