Granted
Chaussée de Waterloo 547
Ixelles · PU/552843 · Permis d'urbanisme privé
Chaussée de Waterloo 547, Ixelles: change of use. Case octroyé, lodged on 14 November 2014. The decision was notified on 1 August 2015, 260 days after lodging. The project creates 48 m² of housing. It comprises 6 dwellings.
transformer les bâtiments avant et arrière notamment modifier la toiture, transformer les volumes arrière, aménager des terrasses, changer l'affectation de l'arrière bâtiment afin d' aménager six appartements48m²
Housing floor area created
6
Dwellings created
| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 14 November 2014 | date the file was received |
| Public inquiry | 23 March 2015 – 8 April 2015 | |
| Consultation committee | 22 April 2015 | |
| Decision notified | 1 August 2015 | 260 days |
| Works started | 9 March 2017 | |
| Competent authority | Ixelles |
Timeline
- Application lodged
- Declared incomplete
- Public inquiry opened
- Public inquiry closed
- Declared complete
- Consultation committee
- Decision notified · Granted
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)