Avenue Stiénon 76
Bruxelles · PU/555074 · Permis d'urbanisme privé
Avenue Stiénon 76, Bruxelles: split into dwellings. Case octroyé, lodged on 16 December 2014. The decision was notified on 23 April 2015, 128 days after lodging. The project creates 127 m² of housing.
inrichten van dakverdieping tot woning (reeds uitgevoerd) en verbouwen van handelsgelijkvloers tot woning (totaal 4 wooneenheden)| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 16 December 2014 | date the file was received |
| Public inquiry | 13 February 2015 – 28 February 2015 | |
| Consultation committee | 10 March 2015 | |
| Decision notified | 23 April 2015 | 128 days |
| Works started | 20 January 2016 | |
| Competent authority | Bruxelles |
Timeline
- Application lodged
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 23 m | Tree felling | abattre un arbre en fond de parcelle | 2022 |
| 73 m | Extension or raising | agrandir l'annexe du rez-de-chaussée d'une maison unifamiliale | 2022 |
| 73 m | Extension or raising | agrandir l'annexe du rez-de-chaussée d'une maison unifamiliale | 2023 |
| 76 m | Tree felling | abattre un arbre (Taxus) | 2025 |
| 76 m | Tree felling | abattre un arbre (Taxus) | 2025 |
Other nearby cases : 04/PU/1938365, 04/PU/1973374, 04/PU/1863945, 10/PU/1952082, 04/PFU/1953334, 04/PFU/1921915, 04/PFU/1926551, 04/PU/1917353, 04/PFU/2008835, 04/PU/1991490, 04/PFU/2021134, 04/PU/1986895, 04/PU/2007257, 04/PU/1965906, 04/PU/1927603, 04/PU/1909948, 04/PU/1992132, 04/PU/1932108, 04/PU/1902681, 04/PU/1941088, 04/PU/1820870, 04/SFD/1830926, 04/PU/1971454, 04/PU/1892204, 10/PU/1869413
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)