Rue de la Ruche 032
Schaerbeek · PU/555910 · Permis d'urbanisme privé
Rue de la Ruche 032, Schaerbeek: heavy renovation. Case octroyé, lodged on 30 December 2014. The decision was notified on 8 September 2015, 252 days after lodging.
dans une bifamiliale, rehausser un mur mitoyen, effectuer des travaux structurels intérieurs et aménager une terrasse sur un toit plat en façade arrière| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 30 December 2014 | date the file was received |
| Decision notified | 8 September 2015 | 252 days |
| Works started | 7 October 2015 | |
| Competent authority | Schaerbeek |
Timeline
- Application lodged
- Decision notified · Granted
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 42 m | Tree felling | [CADUC] Abattre un arbre à haute tige dans le jardin ayant subi une taille radicale | 2026 |
| 61 m | Façade and windows | [CADUC] restaurer et mettre en conformité des modifications en façade avant | 2025 |
| 63 m | Heavy renovation | Rénover la conciergerie de l'école 1 | 2022 |
| 63 m | Heavy renovation | Restaurer la salle Musée-Bibliothèque de l'Ecole numéro 1 à Schaerbeek | 2024 |
| 63 m | Heavy renovation | Rénover l'équipement sportif de l'Ecole N°1: créer un pôle sportif avec des espaces de vestiaires, sanitaires et rangeme | 2025 |
Other nearby cases : 15/PFU/1822872, 15/GOU_PU/1917282, 15/PU/1869792, 15/GOU_PU/1841329, 15/PFU/2010596, 15/PU/1832774, 15/AA/1899031, 15/PU/2025027, 15/SFD/1854062, 15/PU/1832788, 15/PU/1868901, 15/PU/1828526, 15/PU/1849391, 15/PU/1863150, 15/PU/1985139, 15/PU/1870173, 15/PFD/1947966, 15/PU/2012468, 15/PU/2042298, 15/PU/1838232, 15/PFU/1968897, 15/PU/1937796, 15/PFU/1825553, 15/PFD/1923615, 15/PU/2022606
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)