Rue Henri Van Hamme 89, Evere: extension or raising. Case octroyé, lodged on 19 January 2015. The decision was notified on 9 July 2015, 171 days after lodging. The project creates 2 m² of housing.
rehausser le toit d'un immeuble de logements.| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 19 January 2015 | date the file was received |
| Public inquiry | 13 February 2015 – 28 February 2015 | |
| Consultation committee | 19 March 2015 | |
| Decision notified | 9 July 2015 | 171 days |
| Competent authority | Evere |
Timeline
- Application lodged
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 0 m | Extension or raising | Mettre en conformité une terrasse en façade arrière _ SANS SUITE. | 2024 |
| 0 m | Extension or raising | mettre en conformité la terrasse en intérieur d'îlot (1er étage) | 2025 |
| 6 m | New construction | Régularisation de la construction d'une maison unifamiliale _ SANS SUITE | 2026 |
| 25 m | Façade and windows | remplacer des châssis de la façade avant | 2024 |
| 49 m | Extension or raising | Mise en conformité de l'extension en rez-de-chaussée et de la modification de la façade avant et mise en place d'un auve | 2023 |
Other nearby cases : 06/PU/2032665, 06/PU/1865190, 06/GOU_PU/1941451, 06/GOU_PU/1936666, 06/PU/1905425, 06/PU/1843384, 06/PU/1938545, 06/PFD/1830227, 06/PU/1899953, 06/PU/1898976, 06/PU/2044933, 06/PU/1995279, 06/PU/1828850, 06/PU/1846237, 06/PU/1821055, 06/PFD/1837007, 06/PFD/1829452, 06/PU/1925270, 06/PU/1865234, 06/PU/1933337, 06/PU/1977290, 06/SFD/1965402, 06/SFD/1892538, 06/PU/1893916, 06/SFD/2009326